WATCH: Cygnet Bridge’s 100ft masts lifted into place by 700 tonne crane by River Nene
The 100ft masts of Cygnet Bridge have been installed by a 700 tonne crane over the River Nene, marking a significant milestone in the bridge's construction.
A major milestone in the construction of the £8.5 million Cygnet Bridge was completed on Friday (November 20) - as the pair of huge 100 foot masts were lifted into place.


A crowd gathered on the banks of the River Nene on Friday morning (November 20) to watch the incredible engineering operation.
The masts were delivered to Peterborough a number of weeks ago, and had been connected together on the Embankment.


On Friday, the 700 tonne crawler crane - one of the biggest of its type in the country, roared into life to lift the giant masts into place.
The crane was so big, it needed a smaller crane to come to the site to help construct it
A team working on a concrete platform carefully positioned the posts into place.




The decking for the bridge - which arrived in Peterborough on Tuesday with a police escort - will be put into place over the coming days.
The bridge, which links Fletton Quays with The Embankment, has received some criticism, with some commentors referring to it as ‘the bridge to nowhere,’ with others saying it is a waste of tax payers money.




The funding for the bridge has come from a range of sources.
The Government's Towns Fund has pledged a total of £2million towards the project. The Department for Levelling Up, Housing and Communities has ring-fenced this money which means the council can only spend it on this project.
Cambridgeshire and Peterborough Combined Authority has contributed £5.4million. The remainder will come from the council’s own redevelopment budget.
The project budget is currently estimated to be £8.3m.
It is scheduled to be finished by the spring next year.