Details revealed of £3.8m revamp of Peterborough's Jack Hunt swimming pool

New details have been revealed of exactly what the £3.8m revamp of Peterborough’s ageing Jack Hunt Swimming Pool will entail.

In July, Peterborough City Council’s cabinet approved a funding request of £2,200,000 for the refurbishment and which is to be supported by a £794,000 grant from Sports England.

The pool was built in the 1970s and the council has been told that a number of the 50-year-old facilities need updating or replacing to allow the venue to be able to continue hosting swimmers into the future.

The work is expected to start in Spring 2027 and be completed by September 2027.

Jack Hunt School.placeholder image
Jack Hunt School.

A planning application for the internal reorganisation and first floor extension of existing sports hall in order to create a new fitness suite has now been submitted by Evans McDowall Architects.

The developments include:

- Building a first-floor extension to above the changing facilities to provide a new fitness suite on both floots

Reconfiguring the layout of the existing changing facilities to improve layout and functionality

- Installing new windows and doors

Re-cladding the building in order to reflect the appearance of the most recent additions across the school campus

- External hard landscaping

Access to the proposed fitness suite would be through the existing school campus.

For the wider community, this will be via the main school reception with access cards provided for bookings. A receptionist will manage the access area until 9:30pm.

The application states: “The proposals seek to enhance the school’s existing fitness provision for pupils whilst also creating facilities that can be used by the wider community.

"The proposal has been designed to work within the constraints of the existing site and in consideration of its immediate setting, aiming to replicate the scale and massing of buildings within the curtiliage of the school. The scale and massing of the extension will form a two storey building and therefore remain entirely in keeping with existing building stock."

A previous council report noted: "Failure to invest in this asset will result in operational property issues which will further result in unplanned closures.”

The application can be viewed on Peterborough City Council’s planning portal, search using reference 26/002835/FUL.