Everything to know about Peterborough’s Cygnet Bridge project as construction to begin in 2026
Construction of a new footbridge across the River Nene is on course to begin next year.
Cygnet Bridge, as it was named following a consultation in summer 2023, will link Fletton Quays to the Embankment in Peterborough.
Peterborough City Council hopes the new bridge will assist in creating a ‘walkable, liveable city’ and reduce pressure on city centre traffic routes.
The authority said it would also directly link people to the Goods Shed, a former derelict railway building that is to be developed into a food and drinks hall.


How much will Cygnet Bridge cost?
Initially, the bridge had an estimated cost of £6.3 million with contributions from the city council, Cambridgeshire and Peterborough Combined Authority (CPCA), and the government’s Towns Fund.
But in January this year, the city council asked the CPCA to provide additional funding of £2 million due to complex design modifications and higher costs for required sewer diversions than initially projected, bringing the total estimated cost of the project to £8.3 million.
Despite this estimate, the council confirmed in November that it was awaiting an updated programme and cost profile following a CAT 3 design check, meaning the projected cost could change again.
A freedom of information request submitted by the Local Democracy Reporting Service in November revealed that the council had already spent approximately £1.2 million on the project prior to its construction.
The council said this money was spent on detailed design and structural checks as well as professional fees.
The total funding for the bridge so far includes £2 million from the government’s Towns Fund, £5.4 million from the CPCA and the rest from the city council’s redevelopment budget.
When will Cygnet Bridge be built?
Sewer diversion works for the bridge began in September this year, but the main construction work will not begin until 2026 to avoid poor weather.
This is despite an original estimated completion date of November 2024 in the Outline Business Case for the project.
The bridge construction was at one point due to be completed by summer 2026, but this is now unlikely to be the case.
The council previously said it was committed to ensuring that the bridge was “both cost-effective and sustainable” in the long term.
A completion date has not yet been confirmed.
Reaction to the bridge
During the city council’s initial consultation on the bridge, 566 people completed online surveys and 165 people engaged at public pop-up events.
The surveys found that 79 per cent of the people who responded supported the bridge and 55 per cent said the bridge would encourage them to walk or cycle more.
Planning approval was granted for the bridge in December 2024.
The following month, the plans drew criticism from residents when interviewed by the Local Democracy Reporting Service, with some questioning the need for the bridge and its value for money.
Councillor Nick Thulbourn, the council’s cabinet member for growth and regeneration at the time, said the bridge was a “vitally important piece of infrastructure”.
“We understand that people may not realise the full benefit of a bridge now, but they will once this area of the city develops further,” he said.
The £2 million Towns Fund money is ring-fenced, meaning the council can only spend it on this project.