Cambridgeshire drivers set for boost as £1.5 billion A14 scheme to finish early

Cambridgeshire drivers are set for a boost - with the long awaited A14 upgrade set to open six months early.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

The £1.5 billion scheme - the biggest road project in the country - was originally planned to open to traffic by the end of 2020.

Today Highways England said it plans to open the A14 improvement, which will see faster journeys between Cambridgeshire and the Midlands, ahead of schedule this spring.

Hide Ad
Hide Ad

The good news follows the recent December opening of a part of the 21-mile scheme – a new 12-mile bypass south of Huntingdon – a whole year early. Already, the bypass has been used to make more than five million journeys.

The new A14 will open earlier than plannedThe new A14 will open earlier than planned
The new A14 will open earlier than planned

Highways England chief executive Jim O’Sullivan said: “The A14 is a vital route used by 85,000 drivers every day and including more than 21,000 hauliers transporting essential goods around the country.

“Opening this scheme more than six months early and on budget shows what the UK construction industry can achieve working with Highways England on the Strategic Road Network. I would like to thank them for their focus on our joint success and for their one team approach.

“Also, I would like to thank road users, residents and stakeholders for their patience and support during our work. This road is not just a piece of national infrastructure - it brings benefits to the region and local towns and communities too.”

Roads Minister Baroness Vere said:

Hide Ad
Hide Ad

“I’m delighted that the A14 upgrade will open ahead of schedule, not only meaning drivers will benefit from quicker and safer journeys sooner, but also ensuring that key access between the region’s ports and the West Midlands will be boosted.

“Investing in key transport links such as this is part of this Government’s plan to level up access across the country, ensuring all regions are better connected and improving journeys for all.”

Work on the project began in November 2016, and has employed around 13,000 people in total, with up to 2,500 working on site during the project’s peak who have been working hard to deliver an early opening for traffic on the new A14.

Besides the Huntingdon southern bypass, the project includes an upgrade to the A14 between Swavesey and Milton, and a new local access road, the A1307, which runs parallel to it between Cambridge and Godmanchester. Approximately 24 miles of new routes for cyclists, walkers and horse riders are also included in the scheme.

Hide Ad
Hide Ad

The spring opening date will mark the end of permanent roadworks and reduced speed limits on the new A14 and the A1307, but the project team will still need to carry out a number of completion activities such as landscaping, installing some of the new technology, and work in the verges. To carry out this work safely, some temporary overnight closures or off-peak daytime lane closures will be needed.